Couteaux bridge

WORKS

 

 

 


Map

Utility services are diverted in order to prepare the site for works

30 January 2006. Works on the Couteaux bridge will start shortly.

Before engineering works can start, the various utility services passing through existing bridge have to be diverted. This phase is currently under progress.

Works on the bridge itself are scheduled to start on 6 Febuary 2006.
They are expected to last 18 months, with reopening planned by May 2008.

 

Pont des Couteaux

Aerial view of the Couteaux bridge