Rebuilding of Grande Vigne bridge
Unlike other bridges in the BlueLinks project, the bridge will be rebuilt, not only restored.
Works scheduled until June 2006.
Estimated cost : 1 Million Euros.
- First week of May 2006: installation of iron deck.
- Week of 8 February 2006: removal of bridge deck.
- 30 January 2006: start of demolition of existing bridge.
- 26 January 2006: start of works on Grande Vigne bridge.
|